PROJECT
The main goal of this project was replacing two air-cooled chillers which could not properly meet the cooling needs of the industrial plant, forcing the client to constantly face insufficient cooling issues, especially in the summer season. The requirement was to remove two chillers out of the four existing chillers and install two new chillers, or simply install just one higher capacity chiller.
PRODUCTS
1x EWAH-TZ
Total Cooling capacity: 1400 kW
THE CHALLENGE
The client has great attention towards reducing their environmental impact and needed technology that could easily comply with their global HSE policy, which does not allow installation of equipment with GWP higher than 50.